Hollister Avenue Bridge Replacement

Print
Press Enter to show all options, press Tab go to next option

Description

This project will replace the Hollister Avenue Bridge over San Jose Creek. The new bridge will have a 100 year storm flow capacity and will be designed to fit with the recently completed San Jose Creek Capacity Improvement & Fish Passage project.

Purpose and Need

Laboratory testing has confirmed that the existing bridge was constructed using reactive aggregate and is deteriorating rapidly. The existing bridge does not conform to current design standards and retrofitting is not feasible. The replacement of this bridge also completes the San Jose Creek Capacity improvements project by removing the geometric constraints on the channel under the existing bridge.

Strategic Plan Goals

Implement Citywide Capital Improvement Program

Emphasize Old Town Revitalization

Funding Sources

Funding for this project is a combination of sources, including Highway Bridge Program (HBP) funds. The project will be funded 88.53% by the HBP.

Current Phase

The City of Goleta completed a Draft Mitigated Negative Declaration (DMND) for the project in December 2014. The public comment period ended in January 2015. The Final MND was approved in August 2015. Final design, right of way and permitting phases are currently underway. Construction is anticipated to begin in FY 17/18 at the same time as construction of the City’s Ekwill Street and Fowler Road Extensions Project. 

HollisterAvenueBridge_MND_FINAL

PROJECT MANAGER:

Rosemarie Gaglione, P,E,
rgaglione@cityofgoleta.org
805-961-7569

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Flash Player QuickTime Windows Media Player Microsoft Silverlight Word Viewer Excel Viewer PowerPoint Viewer