Goleta, CA
Home MenuProject Connect
Project Connect Construction is Underway
Project Connect, the City’s largest capital improvement project, is enhancing pedestrian access and safety, improving road conditions and building critical linkage through Goleta while increasing stormwater flow capacity in San Jose Creek under Hollister Bridge. Project Connect requires numerous right-of-way acquisitions and permits as well as close coordination with many local agencies including Caltrans, City of Santa Barbara, and the County of Santa Barbara.
View maps of the different project areas using the links below:
Construction Update: November 2024Hollister Avenue traffic lanes between the southbound Highway 217 offramp and Kellogg Avenue have been adjusted to accommodate a safe working space for Project Connect construction of the new Hollister Avenue Bridge over San Jose Creek. Traffic has been shifted to the south side of Hollister Avenue and reduced to one lane of traffic in each direction. Construction crews will be working in the northside Hollister Avenue lanes. This work and the associated traffic shift are scheduled to continue into early 2025. All construction zones are closed to the public and should not be accessed during active construction activities or while unattended.
View a larger map of the construction here. Please move through the area with caution and care as the new lane alignment will require an adjustment period. Share the road with pedestrians and bicyclists and reduce speeds for safety. |
For additional information, or questions, please email Connect@CityofGoleta.org or call 805-690-5116. |
Project Areas
Project Connect includes three project areas: Hollister Avenue, Ekwill Street and Fowler Road. Click the arrows below to learn more about each project.
Frequently Asked Questions
Environmental Requirements
As with all construction projects, the City was required to assess the project’s environmental impacts in advance of construction. Mitigation efforts were incorporated into the engineering design and approved by regulators, and the construction team abides by environmental requirements for air quality, nesting birds, land clearing, water way work, among others.
Project Connect construction requires the removal of certain trees and plants within the project area. However, the City of Goleta is committed to creating and enhancing its sensitive habitats and the environmental landscape in a manner that exceeds the total acreage and plant species impacted by Project Connect. The implementation of the City’s comprehensive mitigation efforts will result in a more diverse, abundant and expanded native ecological footprint within the City of Goleta.
By the Numbers
When complete, plant and biological restoration efforts will result in:
- More than 5 acres (5.34 acres) of enhanced or newly created riparian habitat and areas where additional trees will be planted, which is a net gain in the acreage of coastal and non-coastal riparian habitat within the City of Goleta.
- 10 trees planted for every tree removed, for a total of 1,980 new California native trees
- Restoration or creation of riparian habitat at a ratio of 3:1 for permanent riparian impacts and 2:1 for temporary riparian impacts caused by the project
The mitigation plantings will be completed at the end of the construction project in 2026.